Hyperscale Data Centre

Scandanavia

Client: Hyperscale Date Centre
Size: 30MW

We were involved as Project Managers on the Design and Contract Management on a New Build Hyperscale Data Centre for a large Global Client.

The project was challenging from many aspects not least the location and lack of available local contractors and suppliers. The worldwide supply chain was leveraged to maximum effect during the design phase of the project.

The data centre was a greenfield site which utilised free-cooling from the available local ambient resources.

The client requirements were to construct the Data Halls in as short a timeframe as possible. This was achieved by looking at fast track construction solutions particularly in the area of off-site fabrication to minimize onsite installation time.

A collaborative approach, notably pre-design workshops involving the architectural, MEP design team and contractors was crucial. Off-site testing and witness was also an essential component of the successful solution.

The Project was achieved to programme and budget in a safe environment and the client has continued to build using the same model of design and construction.